HS2 - Notice of ground investigations near Hams Hall

Published on Thursday, 4th July 2019

Western Power Distribution will be undertaking ground investigation survey works in preparation for high voltage electricity cable diversions necessary to build the new railway.

Western Power Distribution need to divert existing assets within land adjacent to the A446 Lichfield Road, North of Faraday Avenue, Hams Hall to allow HS2 works to begin.

There will be no disruption to local traffic and the work will take place on private land.

Hs2 a446

Duration of works

Works will being the week commencing 15 July and will last for approximately one week.

Our working hours will be 8am to 6pm Monday to Friday.

We may be on site one hour, either side of these times, for set-up and close-down.

What we will do

Keep all sites safe and secure. Ensure all contract vehicles use agreed routes.

Ensure noise levels are kept to an absolute minimum for the duration of the works.

Access the work location from the A446 Lichfield Road only and not via Faraday Avenue.

If you have a question about HS2 or our works, please contact the HS2 helpdesk on 08081 434 434 or email HS2enquiries@hs2.org.uk